Monday, 16 September 2019 12:36:10

RBM

RBM at Baku Aquatic Center

on Tuesday, 29 September 2015.

European games swimming pool radiant heating system made with RBM products

REALIZATION DATE

28/02/2015

PURCHASER

AZCOND, Baku – Azerbaijan (www.azcond.com)

DESIGN WORKS

AZCOND, Baku – Azerbaijan (www.azcond.com)

INSTALLATION

AZCOND, Baku – Azerbaijan (www.azcond.com)

DISTRIBUTOR

AZCOND, Baku – Azerbaijan (www.azcond.com)

PLACE

International Olympic Swimming Pool, by BAKU AQUATIC CENTER. Inauguration date February 2015 and selected site for the 2015 EUROPEAN GAMES

PROJECT DESCRIPTION

Floor Heating Project on a total surface by 6,000 sqm. Main heated floors around the 3 main pools: Diving Pool, Central Olympic Pool and Training Pool. We will be also heated some other spaces as: Locker Rooms, Shower Rooms, Sauna and SPA, Gym, and Service Rooms.

RBM PRODUCTS USED FOR THE PROJECT

  1. RBM Kilma-flex PE-Xc pipes 17 x 2: 41.000 mt
  2. RBM Kilma Form 35 mm insulating panels: 6.630 sqm
  1. RBM Kilma polymer manifolds and housing boxes: 55 pcs (from 3 to 12 ways)
  1. Ball valves: 3.700 pcs (from ¾” to 2”)
  1. Y strainers: 610 pcs (from ¾” to 1”)
  2. 4 ways motorized zone valves : 1.000 pcs
  1. Other installation components (press-fittings, corrugated insulating pipe, perimeter joints, pipe-supporting plastic bends)

DESCRIPTION OF THE FLOOR HEATING SYSTEM

The floor heating system works normally by a temperature from 40 to 45° C, in order to make very comfortable all the area surrounding the swimming pools and also improve the dry action on the floor surface.